Every work day logged by date, phase, crew, and completion status.
Sep 5 · Sat
Erosion Controls
Silt fence + FDEP-compliant floating turbidity barrier installed pre-demolition. Erosion / sediment control measures verified per permit conditions.
Complete
Sep 7 · Mon
Utility Remediation
Site plumbing remediation completed. Coordination with subcontractors for Week 2 electrical follow-up scheduled.
Complete
Sep 8 · Tue
Drainage Prep
Temporary electrical service isolation. Ground-protection matting deployed. 103 LF multi-cell subsurface drainage prep using hydro-reduction methodology. 2nd payment received.
Complete
Sep 9 · Wed
Demolition
Landward CBS retaining-wall partial demolition — 10' × 3'-9" × 8" section. Controlled soil excavation along landward perimeter (5'–15' offset).
Complete
Sep 10 · Thu
Damage Discovery
Damage assessment upon footer exposure — identified 41 sq ft hole through footer + 9' V × 4.5' H × 8" D crack propagation zone, repair mandatory for stability, 2 sides (documented for CO-001 scope).
Incident Logged
Sep 11 · Fri
Demobilization
Debris cleanup, cut-chip concrete removal, machine loading, site wash-down, demobilization — 47' × 3'-9" × 8" partial bulkhead removed per engineering. End-of-week inspection performed. Storm-induced electrical short at 15:00 — Pedro Electric dispatched, safe-off executed. No injuries; concrete & drainage scope unaffected.
Safe-Off
Sep 14 · Mon
Week 2 Start
Pedro Electric site revisit — storm-related short traced + GFI outlet installed (new). Silt fence + turbidity float upgraded. Demo commenced same day under the approved parent contract (Est #PB-2026-173). CO-001 remains pending approval.
Complete
Sep 15–16 · Tue–Wed
Demolition + Rebar Drilling
Demo fully complete for approved initial agreement. Rebar drilling initiated — 6" embedment depth per Sika AnchorFix-3001 specification; epoxy set per manufacturer 4-4-4 hole-clean protocol.
Complete
Sep 17 · Thu
Rebar Install + Erosion
50% of rebar installed thus far. Ditch re-dug along landward perimeter — erosion mitigated; drainage flow path restored. Rebar cross-section horizontal sections tied in per engineering specs.
Complete
Sep 18 · Fri
Rebar Install + Tie + Epoxy Complete
Rebar installation, tying, and structural-epoxy set — 100% complete. Full mat set into existing footing (Sika AnchorFix-3001, 4-4-4 clean protocol, 6" embedment). Debris cleaned up. End-of-week EOR walkthrough — reinforcement layout verified and released for coating + pour.
Complete
Sep 19 · Sat
Formwork Started
Formwork started today (Saturday). Heavy-duty formwork tied and braced to hold single-pour geometry per Reference Plan on initial CBS wall. Rebar fully cleared for Monday coating.
Complete
Sep 21 · Mon
CO-001 Approved · Rebar Ties + Gap Corrections · Armatec + SikaTop Applied · 50% Formwork · Silt-Fence Adjustments
CO-001 approved today by Building Management. Rebar mat advanced — additional ties addressed and gaps between rebars corrected. Sika Armatec 110 EpoCem + SikaTop 123 Plus applied to all installed rebar. 50% formwork complete. Silt fence adjustments performed. Change Order CO-002 issued for seawall damage repair — 65.69 sq ft cut · rebar · epoxy · tie · form · pour to spec per engineering ·
Complete
Sep 22 · Tue
Deposit Received · Rebar Finish · Armatec Rebar Coating Complete
Deposit received. Remaining rebar installed and mat straightened. Sika Armatec 110 EpoCem rebar coating — complete across full reinforcement mat. Formwork bracing continued on bulkhead 47 LF section.
Complete
Sep 23 · Wed
Bulkhead Formwork 80% · Wood Forms Bent to Arc Curvature · Weather Half-Day · CO-002 Pending
Bulkhead 47 LF section formwork at 80%. Wood forms bent on-site to match arc retaining-wall curvature per engineering geometry. Weather affected work — half-day shift. Pour delayed accordingly to Sat Sep 26 · 8 AM (weather permitting). Awaiting CO-002 approval from Building Management for seawall damage repair scope (65.69 sq ft). Pre-pour EOR QA Thu Sep 24.
In Progress · Half-Day
Sep 30 · Wed
CO-001 + CO-002 Approved · Draw 1-of-3 Deposits Received (Both) · 57 LF Removal Ready (Partial CO-002) · Pour Confirmed Fri Oct 2 · 1 PM (subsequently rescheduled Mon Oct 5 — see Oct 2 entry)
Both CO-001 and CO-002 approved by Building Management today. Draw 1-of-3 deposits received on BOTH change orders — Wed Sep 30, 2026. 57 LF of CO-002 removal demolished + prepped and ready to pour (partial CO-002). Formwork complete across bulkhead + partial-CO-002 footer-form zones. North-section formwork resumed and finished per weekend stand-down. Pre-pour EOR QA scheduled Thu Oct 1. Bulkhead concrete pour on schedule — Friday October 2, 2026 · 1:00 PM batch window under the pour-3-sections same-run amendment (bulkhead 47 LF + 57 LF partial CO-002 in one continuous batch; balance CO-002 scope follows on subsequent pour). Pour subsequently rescheduled to Mon Oct 5 · 1 PM — see Oct 2 activity entry.
Complete
Oct 2 · Fri · 2 PM
Rebar + Armatec Epoxy Coating 100% Complete · Pour Rescheduled Mon Oct 5 · 1 PM
Rebar install and Sika Armatec 110 EpoCem epoxy coating 100% complete at 2:00 PM today across bulkhead 47 LF + 57 LF partial-CO-002 reinforcement mat. Formwork bracing verified. Pre-pour EOR QA sign-off received Thu Oct 1. Bulkhead concrete pour originally scheduled Fri Oct 2 · 1 PM — rescheduled to Monday October 5, 2026 · 1:00 PM batch window per field-condition / weather window. Pour-3-sections same-run amendment unchanged: bulkhead 47 LF + 57 LF partial CO-002 in one continuous batch · coastal-exposure admixture · matched compressive spec. Balance CO-002 scope on subsequent pour. Triggers CO-001 + CO-002 milestone #2 draws upon EOR post-pour sign-off.
Scheduled