Why We Build · 844SEAWALL
01 · Threshold

A seawall isn't infrastructure. It's a thirty-year promise to the land behind it.

This page is a short film in scroll. Five chapters, each a declarative sentence. By the end you will understand what we build, how we build it, and — the only question that actually matters — why.

Est.September 2019
RangePalm Beach → Florida Keys
DisciplineMarine · ACI 318-19 · C2
On RecordFirst documented 3DCP in Florida
StandardOn Time · On Budget
Scroll · 05 Chapters
01 · OYSTER TOE 02 · SEAGRASS MEADOW 03 · MANGROVE FRINGE 04 · LAST LINE SECTION A-A · LIVING SHORELINE · NTS
02 · The Reef · Priority One

The reef isn't scenery. It's the first client on every project.

Before we specify a yard of concrete, the ecology is already doing structural work. An oyster toe breaks the swell. A seagrass bed binds the sand. A mangrove fringe traps the surge.

Half of what a seawall must do, a living shoreline has already done — and continues to do, long after the pour has cured. So we design the ecology first. The engineered wall is the second argument, not the first.

An ecosystem that doesn't bill by the hour.
Wave absorption
50%
Oyster-reef toe breaks swell before it reaches the wall
Carbon rate
7×
Mangrove per hectare vs. terrestrial forest
Reef baseline
14k yr
Caribbean coral framework over Holocene epoch
Priority One · The reef comes first · the wall is the follow-through
03 · The Wall · Priority Two

The concrete isn't decoration. It's the sentence after the reef has made its argument.

Where the ecology ends, the discipline begins. Five thousand pound-force concrete. Epoxy-coated reinforcement on eight-inch centers. A tie-back that reaches ten feet into dry land. Drainage behind the wall so hydrostatic pressure never has a case to make.

We design the whole section — cap, body, toe, anchor, drainage — as a single argument with the Atlantic.

A wall is a slow conversation with gravity.
Strength
5,000 psi
Marine-grade mix · ACI 318-19 C2 exposure
Steel
#5 @ 8"
Epoxy-coated ASTM A775 on 8-inch centers
Design life
50+ yr
Specified to outlast the mortgage, then the grandchildren
Priority Two · The wall is the last word · and it has to hold the line
CAP · 2' × 24" #5 @ 8" O.C. WEEP TOE · FOOTING TIE-BACK · 10' DEAD #57 DRAINAGE STONE HYDROSTATIC · 2.5k PSF 30 FT SECTION B-B · SEAWALL · 1" = 4'
04 · The Method

Eight phases, countersigned in sequence.

A sealed Take-Off Agreement. An Engineer of Record whose signature releases each gating phase. A Weekly Progress Report delivered every Monday. A live Owner-facing portal that updates the day each pour is placed. The discipline that governs a Fortune-500 project governs your waterline too.

The discipline is the standard. The scale is the only variable.
01
Mobilization
Site protection, safety plan
02
Demolition
Sawcut, remove, haul
03
Reinforcement
Rebar mat, anchor epoxy
04
Formwork
Line, grade, brace
05
Drainage
Weep, filter stone
06
EOR Sign-off
Pre-pour quality
07
Pour
Place, vibrate, cure
08
Walkthrough
Strip, inspect, close
Governance
Sealed Take-Off
Every scope line, every quantity, every unit price — stamped and locked
Oversight
EOR Sign-Off
Engineer of Record countersigns each gating phase before the next is released
Transparency
Weekly Reports
Monday-morning progress report · dated, phase-indexed, photo-sourced
Record
Live Portal
Owner-facing portal updated same-day as each pour, photograph, and change order
The paper trail that governs a Fortune-500 build governs your seawall too.
05 · The Covenant

Because this is our coast too.

We grew up on these beaches. We raised families on them. Our neighbors' houses sit on the same sand that erodes under ours. The ocean has no quarrel with any of us — but it has gravity, and over fifty years, gravity is a patient opponent.

So we picked this fight the way you pick a vocation: you look at the slow damage, the quiet retreat of the shoreline, and you decide that someone has to build the kind of wall that does its job for your grandchildren too. We decided to be that someone.

On Time. On Budget. Brick and Mortar Company LLC · Est. September 2019 · Palm Beach, FL
844SEAWALL
Brick and Mortar Company LLC · 301 N Ocean Blvd Pompano Beach FL 33062 · 1·844·732·9255 · Florida Licensed · Insured
Est. September 2019 · First Documented 3DCP in Florida · On Time · On Budget